Tag Archives: sr99

After Weekend Closure, a “Mercer East” Construction Update

Mercer_Construction_Map_Spring2013

East side of SR 99 Mercer overpass demolished (Photo: SDOT)

East side of SR 99 Mercer overpass demolition in progress (Photo: SDOT)

SDOT map of Mercer/SR 99 construction routes for spring 2013

Seattle’s department of transportation put in some swift demolition work over the July 4th holiday weekend, reopening SR 99 early Sunday morning and then Mercer Street by the afternoon, beating their 5 a.m. Monday morning target handily. On July 3rd, there was an eastern side to the SR 99 overpass that spans Mercer Street; now there isn’t. (If you’re on Facebook, make a point of Liking the SDOT page, which alerts you to all sorts of traffic impacts around the city.)

Traffic had been rerouted well in advance of the actual demolition, so drivers won’t notice any difference in the chaotic traffic pattern due this piece of the work on the Mercer Corridor Project. Now SDOT will build a new half-an-overpass, allowing a wider Mercer Street, and once that’s done — setting the girders in place will likely prompt a weekend closure of Mercer and at least the northbound lanes of SR 99 — demolish the western side (again, a weekend closure). That should come sometime before October.

But that’s it for major disruptions — there will still be detours and lanes shifted occasionally, but you won’t lose access entirely.

At times like this, it’s perhaps a good idea to refresh your memory on what the point of it all is. SDOT provides a full description of the Mercer Project here. In terms of motorized traffic flow, the goal was to remove a righthand dogleg for drivers exiting I-5 toward Seattle Center. In its finished state, Mercer will have three eastbound and three westbound lanes. But the wider Mercer Street will also allow for wider sidewalks on both sides, as well as a separated, two-way bike path on the north side of Mercer.

Both of WSDOT’s Seattle Megaprojects Off to a Bumpy Start

Giant cranes lift the 57.5-foot-diameter cutterhead into place on the SR 99 tunnel boring machine in Japan. (Photo: WSDOT)
Giant cranes lift the 57.5-foot-diameter cutterhead into place on the SR 99 tunnel boring machine in Japan. (Photo: WSDOT)

For most of 2012, the Washington Department of Transportation was watchdogged by KOMO News because of cracks found in new pontoons for the new 520 bridge. Now the Seattle Times‘ Mike Lindblom reports that Bertha, the 7,000-ton tunnel boring machine, purpose-built for digging the SR 99 tunnel beneath Seattle, sustained damage during its initial testing in Japan.

A January 23, 2013, update from WSDOT read, “She was performing well until last week, when crews discovered that something wasn’t quite right with her main drive unit, which rotates the cutterhead. It appears there was insufficient clearance between a rotating and stationary portion of the main drive unit, which resulted in damage to some of its components.”

Said Lindblom: “Testing was to be finished Dec. 25. As of this week, Hitachi Zosen crews in Osaka are disassembling and diagnosing the drive system.” (Sidebar: Although Bertha is, for a little while, the world’s largest-diameter TBM, it’s not a Big Bertha reference; the machine is named for Bertha Knight Landes, Seattle’s only female mayor.)

Bertha’s Twitter account has so far made no reference to its need for repair, or who’s paying for it. But in fact taxpayers are not on the hook yet. Seattle Tunnel Partners (STP) doesn’t officially take ownership of Bertha from Hitachi Zosen until the TBM has made it through about 1,000 feet of Seattle soil with no issues. Even then, says  said Linea Laird, WSDOT’s administrator for the Alaskan Way Viaduct Replacement Program, “More than 90 percent of STP’s work will be performed for a fixed price.”

Meanwhile, cracks in pontoons and mistakes in construction continue to plague WSDOT’s 520 bridge replacement project. In December, WSDOT announced that although specified “hooked” rebar had been left out of three pontoons, they would “structurally adequate” anyway. That omission is, of course, troubling because the rebar in question was supposed to help prevent cracking due to stress.

In an earlier update, in mid-December, titled “Continued progress on SR 520 east approach bridge piers,” WSDOT mentioned that part of that progress was tear-down of a new 58-foot-tall concrete column that had been built with too little concrete over its reinforcing steel skeleton. That was on contracting team Kiewit/General/Manson’s dime.

The state has been pressing for an ambitious finish to replacement of the floating section of the bridge, by late 2014, which presumably was a factor in transportation chief Paula Hammond’s decision not to reject the cracking pontoons shipped so far, proclaiming them mostly cosmetic and of no danger to pontoon integrity. But today Mike Lindblom noted on Twitter: